Recalculating the schedule with the company calendar

When you select the Add off days from company calendar checkbox, Sage 100 Contractor reviews the company calendar and updates the schedule when you recalculate.

To recalculate the schedule with the company calendar:

  1. Open 10-3 Schedules.
  2. Select a schedule.
  3. Select the Add off days from company calendar checkbox.